HIGHLIGHTS  >  FEATURED PROJECT
Marcel - Stewart load crop

We worked extensively with the BC Ministry of Infrastructure and Transportation to receive approval for over-dimensional freight movement through the corridor from Stewart, BC on to the BC/Alberta border. On February 13, 2016, as a trial run, Mullen Trucking was on site at the Stewart World Port to receive cargo off the first ship to dock at this new port, the AAL Newcastle. The trial run was a success and we were granted approval to proceed with the project.

There were 7 Lots to arrive at the Stewart World Port, each with multiple Process Units in varying sizes and weights. Over the next several months, and through many joint collaborations, we successfully delivered Process Units to Redwater, AB. This was not without its challenges however. There were last minute changes, narrow bridges and wildlife to contend with; as well, all travel through BC was limited to night time hours with all sorts of weather conditions!

The following are excerpts taken from a letter written by the customer to Mullen Trucking:

“Safety is the most important part of our day to day activities and I am proud to say that Mullen completed this scope, consisting of over 22,000 man hours and 1,100,000 kms travelled, without incident! Congratulations on that success….This level of achievement shows an unparalleled commitment from all parties! Thank you.

“Lastly, and certainly not least, please pass on our appreciation to your field crews! Without their hard work and dedication, this successful execution would not have been possible. To perform this, and do so safely, shows their level of commitment to your excellent safety culture. They were always professional and consistently showed their commitment to safety first and schedule second. This significant accomplishment should also be commended!”
More images of this project:

PAST PROJECTS

Scheuerle Trailer
Check out our new Scheuerle Trailers! January 4, 2016

After much anticipation Mullen Trucking has received their two brand new Scheuerle trailers! With the addition of the 13 Axle Platform Scheuerle Trailers to our Heavy Haul Fleet we are able to offer a service similar to that of a standard 13 Axle trailer, but with many more benefits! Our Scheuerle Trailers are designed using […]

10 axle FSD
Generator Replacement Project March 4, 2015

Mullen Trucking was awarded with a Generator Replacement project early in 2014. We moved approximately 65 loads in varying sizes, with the  largest weighing in at 139,000 lbs on a 13 axle trailer, from Vancouver, BC to Saskatoon, SK. Mullen Trucking delivered all loads on time and claim free, and wrapped up the project in November […]

RAIL CAR 00
Heritage Mail Express Rail Car July 11, 2014

Mullen Trucking moved a Heritage Mail Express rail car from our yard in Aldersyde, AB to the privately owned Champion Rail Park in Aldersyde, AB.  This Mail Express rail car arrived at Mullen Trucking on the rail and required 2 cranes for the offload and reload onto our equipment. This was no easy task; the dimensions […]

6 Super Loads of Coolers – Catoosa, OK to Fort McMurray, AB May 29, 2014

In the second quarter of 2014 we moved three Cooling Towers from Catoosa, OK to Fort McMurray, AB. These Cooling Towers were so large they had to be broken down into 6 Super Loads! The loaded dimensions of each load were 92′ L x 23′ W x 15’8 H and 133,000 lbs. Routing at these dimensions […]

Heavy haul transportation
Northern Alberta SAGD Project – Anzac, Alberta September 1, 2013

In early 2012, our client began construction on a steam assist oil recovery plant just south of Fort McMurray, Alberta. Mullen Trucking is proud to have been a part of this project from the outset and throughout. To date, we’ve hauled over 1200 (mostly oversize) loads of plant construction materials from all over North America […]